Importing programme in P6

1 reply [Last post]
Kinnar Patel
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 7 Jun 2006
Posts: 24
Groups: None
Hi Everyone,
I ahev two questions to import programme in Primavera P6.
1. Is it possible to import to programme without importing calendar ?
2. Is it possible to prevent calendar go global after importing programme.
Help will be much appreciated.
Thanks in advance.
Regards,
Kinnar

Replies

Shahzad Sikandar
User offline. Last seen 7 years 1 week ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
delete calander (in P6) after import if you dont need it..

change the calander status to project from global if you dont want it to be Global...

shahzad