Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

OD & RD Equal Zero When Converting from P6 to P3 (????)

2 replies [Last post]
Benjamin Mora
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
My issue is that when I am using P6 and converting to P3 the OD & RD become zero in the P3 version of the schedule.

Here are my settings:
-All tasks = physical % Complete
-Drive Activities Dates by Default = unchecked
-Duration Type = Fixed Duration & Units\Time
-All units are zeroed out
-Recalculate Actual Units & Cost when Duration % complete changes = unchecked
-Link Budget & At Completion for not Started Activities = Checked
-Reset Remaining Duration & Units to Original = Checked.
-All activities = Task Dependent.

By the way, this schedule was originally a conversion from P3 that went to P6 and is now going back to P3.

Any clues?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Ben you are not an idiot you caught the problem and solved it. I believe that during the conversion dirve activity dates by default was checked in p6 and this make the resource in p3 a driving resource.

Benjamin Mora
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
Disregard because I am an idiot. In the Assignments window, each assignment needed to have the Resource Driving box unchecked. Problem solved.