Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

S Curve

5 replies [Last post]
CRAIG ASHLEY
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 10 Mar 2005
Posts: 6
Liker others i would appreciate any info available on how to create an S Curve in P5/P6 please. Generating a report for the dates req’d seems very difficult. Any help / guidance will be greatfully received.

Replies

Amreshwar Shukla
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 6 May 2003
Posts: 53
Groups: None
Dear Mark,

Can you please explain the steps involve in making the S curve thru the Crystal Report.

Thanks in advance.

A.S.Shukla
Mark Porter
User offline. Last seen 1 year 19 weeks ago. Offline
Joined: 8 Aug 2007
Posts: 55
Groups: None
Hi Craig,

Based on the RVP notes issued by Oracle/Primavera, Version 7.0 will enable you to do early & late curves @ the activity level without the need to export to excel.

If your company is in maintenance, it is now available to download via the Oracle website: edelivery.oracle.com

We will be switching across in the next couple of weeks & I’m looking forward to comparing its functionality to the old V6.2.1.

Failing that...

The very best way is via an application like crystal reports, etc...

Alternatively, the next best way to create the S-curve is still by a time distributed report that is saved as a csv file, though I must admit that getting a late spread of hrs or costs at the activity level requires a bit of a work around (I usually set my primary baseline to it’s late dates & gather my early dates from the project baseline).

Another way is to run a report at the resource assignment level, and just group via the activity name (Activity Id doesn’t show up 4 some weird reason). That way you can get the remaining early & late date, but unfortunatly you can’t get the EV at the resource assignemnt level.

Hope this helps

Kind Regards

Mark Porter
CRAIG ASHLEY
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 10 Mar 2005
Posts: 6
Thankyou for that reply Alexandre, however, I would like to know the easiest way to create an S Curve (with the data from P5/6)in Excel. As your aware I need to be able to get the early, late and planned dates from P5/6 in to a table and then create the curve. Is there an easier way than creating a report to generate the dates I need?

Thanks,

Craig