summary totals in p6

3 replies [Last post]
glen staunton
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 18 Aug 2005
Posts: 10
Groups: None
Anybody come accross a possibly glitch with the P6 summary totals that they have had resolved.

On a 5 day working week calender I’m getting a total of 308 days when the start date and the end date of the summary band are 09/11/09 and 02/06/10 respectively.

I’ve checked all the usual suspects, that i’m using the correct duration, calender, summary check box, user preferences etc....

Thanks in advance

Replies

Armana Jones
User offline. Last seen 13 years 7 weeks ago. Offline
Joined: 3 Jan 2009
Posts: 18
it seems your activity calendar and default calendar that used by summary is different.
glen staunton
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 18 Aug 2005
Posts: 10
Groups: None
Cheers Dieter, I did and got the problem fixed! Too many variables in this version of Primavera. I need to create a few filters to run to make sure that what I’m sending out is as I assume!
Dieter Wambach
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Glen

Did you check the default calendar?

Regards
Dieter