PROJECT FINISHED DATE NOT CHANGING.

2 replies [Last post]
Shahzad Ahmad
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
HI -ALL

I AM UPDATING MY PROJECT SCHED.IN P6

SOME ACTIVITY HAS STARTED BEFORE TIME.

WHER I HAVE GIVE THEM START DATE AND % COMPLT. REMAINING DURATION ETC..

HOWEVER AFTER PRESS F9 PROJECT FINSHED DATE STILL SAME AS BL SCHED.

THANKS FOR ADVISE.


Replies

Shahzad Ahmad
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hello Mr.Diego

Thanks for your reply.

This is valid reply from you in my schedule all updated activity are not critical thats why finished date of project not reflecting.


Best Regards

Shahzad


Diego Henriquez
User offline. Last seen 13 years 44 weeks ago. Offline
Joined: 3 Apr 2009
Posts: 6
Groups: None
Hi Shazad

Your project completion date will only change if an activity in the critical path changes.
You can have a delivery or future event dictating the completion date of your project, and if so, you can commence all the activities aerlier that you want to, but the critical path will remain unchanged.