Timesheet Actuals

5 replies [Last post]
Sue Chambers
User offline. Last seen 14 years 30 weeks ago. Offline
Joined: 7 Sep 2006
Posts: 43
I am trialing the Primavera timesheets and when we have processed them we apply the actuals to the plan but if we then schedule the system removes the actuals.
I need to keep the actuals from the timesheets and the ability to schedule.
Any ideas anyone on how to solve this?

Replies

Sue Chambers
User offline. Last seen 14 years 30 weeks ago. Offline
Joined: 7 Sep 2006
Posts: 43
Thank you Joao and Dieter I will try this.

Sue
Dieter Wambach
User offline. Last seen 6 years 52 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Sue
Did you check for "Autocompute actuals"?
Joao Ribeiro
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
Sorry, in P6 is called "Store period performance". Read carefully the manual/help before using in a live database.

HTH
Sue Chambers
User offline. Last seen 14 years 30 weeks ago. Offline
Joined: 7 Sep 2006
Posts: 43
Thanks Joao
What do you mean by close out the period?
How do I close out the period?
Joao Ribeiro
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
Just an idea: Have you tried to closeout the period?

HTH