What is "Activity Resource Assignment" ?

5 replies [Last post]
Armana Jones
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 3 Jan 2009
Posts: 18
Dear friends,
I’m a new user of P6 and in somedays I confused in finding the meaning of "Activity Resource Assignment"? Is it Activity, Resource or other?

Thanks.
Armana

Replies

Armana Jones
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 3 Jan 2009
Posts: 18
Thanks a lot everybody.
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

You’re welcome Rav.

A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Thanks Dear,

Thanks a ton
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Rav,

Resources can be assigned to the same activity more than once. This option can be found in the Project Detail --> Resources Tab under Resource Assignments.

Regards.

A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
It means resource assigned for an activity. There is no such specific option/tab in P6 for activity resource assignment.

There r two things to watch for resource assignment:

1. Go to Edit --> User Preferences --> Calculations.
The calculation tab has two options:
a) With the first option, each resource hours are calculated independently.
b) In second option, total no. of hours assigned to an activity will stay constant and sunsequesnt resources are added or removed from an activity. However, this option doesn’t work, if activity type is FIXED DURATION and Units/Time.

2. Resources can be assigned to the same activity more than once. I forgot now where this option is, but may be somebody from teh forum can help on this.

Wish u a very happy new year

Cheers,

Rav