Problem during imporing to P5 from P3

1 reply [Last post]
arun kumar
User offline. Last seen 17 years 1 week ago. Offline
Joined: 4 Apr 2008
Posts: 28
Dear all

I tried to import P3 project to P5..

However during improting it gives the following statement..

only hourly & daily projects are supported..

I am unable to import the project..

can anyone help me..???

Arun

Replies

Arnold Puy
User offline. Last seen 10 years 38 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

Try to check your Planning Unit in P3. P6 does not support Week & Month for Planning Unit. It is always in Days & Hours.

First try to convert your planning unit in P3 to days prior to import to P6.

hth.