8 replies [Last post]
Ijaz Ahmad
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hi Guys,
I am struggling hard to find how to get S-curve for earned value labour units for different resources, like, boiler maker, fitter, etc.
Your help will be highly appreciated.
Thanks

Replies

Sarah Benjamin
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 7
Groups: None
i think it’s unclear if Ijaz wants the resource curve to show up for each assignment or if they want the resource usage profile. it seems to me he wants the histogram of resource usage.

try clicking on the resource usage profile button, then be sure to adjust the display options so that it will show the current project resources. then pick one and it will show the "s-curve" as a bar chart on the right.
Ijaz Ahmad
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Salah,
Thanks for the reply. But what you have mentioned is missing in Version P5. If you also have version P5 then you can look what I am talking about.
Thanks
Ijaz
Salahuddin Ahmed
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 1 Apr 2008
Posts: 25
Groups: None
Ijaz,

For particular resource "S" curve, please follow the steps,

> Choose project
> Resource assignments
> Select the resource assignment to which you want to assign a resource curve.
> To display curve column, click the display options bar
> Choose columnns customize
> Select curve from the general group and add it to the selected list

I hope this will help you and research for printing options.

Salah
Ijaz Ahmad
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Thanks Salahuddin, your solution worked well for activities but I still have problem of getting S-curves resource-wise like for boilermaker, fitter etc. If you can sort it out please write.
Thanks for your help
Ijaz
Salahuddin Ahmed
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 1 Apr 2008
Posts: 25
Groups: None
Ijaz,

Well i am using P6 and P3 it should be same as p6.

However please check.

Follow the steps for "S" curve.

> View
> Show on Bottom
> Activity Usage Profile
> Right click within the profile and select Cost or Unit
> click on Graph tab and check on calculate average
> ........

I hope this will help you, if not let me know through personel email, i will walk you through.

Regards

Salah
Ijaz Ahmad
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
I am using version P5
Salahuddin Ahmed
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 1 Apr 2008
Posts: 25
Groups: None
Ijaz,

Which version of Primavera P3/P6.

Salah
Glenn Douglas
User offline. Last seen 3 years 12 weeks ago. Offline
Joined: 22 Apr 2006
Posts: 39
Do a search on ’s curves’ in pp, there should be enough info on the threads to help.