Exporting Resources from P3 to P5(P3E)

3 replies [Last post]
Kevin Matthews
User offline. Last seen 14 years 13 weeks ago. Offline
Joined: 21 Jun 2006
Posts: 57
Hello All,

Has anyone found a seemless way to export resources from a P3 schedule to P5. It shouldn’t be this hard ?

Keep planning,
Kevin.

Replies

Rade Bajic
User offline. Last seen 16 years 9 weeks ago. Offline
Joined: 30 Oct 2007
Posts: 6
Try to make excel file and import from it. To have a picture how it should look like try to export some resources from P5 to excel file. Also you can print resource base from P3 to .txt file, open it with excel and use some formulas to format it properly.

Sorry for bad English.
Santosh Bhat
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381
When you import a P3 file, it also imports all the resources that are assigned to activities. If you mean transferring a dictionary from P3 to P5 then yes it is a little more complicated.
Rodel Marasigan
User offline. Last seen 1 hour 10 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
What’s difficult about it? I found it easy and simple. Can you elaborate?