Exporting...

2 replies [Last post]
Andrew Musulin
User offline. Last seen 16 years 35 weeks ago. Offline
Joined: 16 Jul 2007
Posts: 7
Groups: None
Just a quick one...

I know you can export the "Resource Assignments" data to excel via copy and paste, but is there a way to export the "Activity Usage Spreadsheet" to excel?

It would make life a lot easier!

Thanks

Replies

David Kelly
User offline. Last seen 1 year 39 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
You need to use the report wizard to recreate the report, and then "print" it as a .csv file. It will load into excel.
Mangesh Khuspe
User offline. Last seen 28 weeks 3 days ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
andrew i think u can use that excel utility found on p5 cd.
iys same as of RA utility in p3.

cheers