Chainage Diagrams with Linea

2 replies [Last post]
Semra Ormeci
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 10 Jan 2005
Posts: 4
Groups: None
Hello All,

I use Linea software to draw chainage diagrams with data from P3.

Is there anyone who knows the way of drawing both target and actual chainage diagrams together in one sheet? Unfortunately, when I try to transfer two files from P3 to Linea with multi project option in transfer section, programme is turned off. There is no problem when one file is transferred. Is there any other way?

Thank you in advance.

Replies

Semra Ormeci
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 10 Jan 2005
Posts: 4
Groups: None
Thank you,

I have done what you have suggested in your third paragraph. Yes, I agree with you it is not a practical way but at least it is a solution.

Thank you again, best regards.
Santosh Bhat
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381
If you’re referring to LINEA, the old German version, then there is no function to show baseline v. current.

Newer versions of Time chainage software such as Linear Plus and TILOS do allow these functions.

The only workaround that I have thought of is to have a duplicate set of activities that are fixed in position (to simulate a baseline) and to haev activity codes on them that will allow you to display them differently - say as light grey lines.

However I see this as a messy and rather labourious solution. My answer is that a baseline comparison should be done by a standard bar chart and use the time chainage chart to show actual/forecasts only.