Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

earned value labour units

5 replies [Last post]
Richard Bowie
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 13
Groups: None
imported projects from microsoft project, when using standard criteria we do not get a return on earned value labour units, until Activities are 100%complete

any sugestions.

Replies

Richard Bowie
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 13
Groups: None
Thanks dave thats the problem solved.

David Kelly
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
I couldn’t find the fix for this known problem on Primavera’s web site, so I thought I should post it. There IS an issue with earned value calculations in projects imported from MSP. You simply export the project as an XER file and import it again.
David Kelly
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
This is a known issue. Check with Primavera tech support
Richard Bowie
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 13
Groups: None
thanks steven but we’ve tried that with no success.
Steven Oliver
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
In the WBS view, look at the settings on the WBS tab