Hello,

I have uncertainty about when Export a project from Primavera 5 to P3 format. When I open this file in P3,it lose the baseline created in P5?

Thanks,
Mauricio

Replies

Karim Mounir
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
try this:
restore the baseline which u are using in P5 first then export it to P3.