Resources with no budget, but a cost to complete

3 replies [Last post]
Steven Oliver
User offline. Last seen 12 years 29 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
I am trying to assign a cost to complete to a resource, which has zero budget. P3e seems to default to setting the budget = cost to complete. Anyone know how to turn this off ?

Replies

Kevin Button
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Steven

At the project level, select the ’Calculations’ tab and untick the ’Link Budget and At Completion for not started activities’.

Doing this allowed me to have a remaining cost with a zero budget and also allowed a remaining duration to be different from original duration for non started activities.

Regards
Steven Oliver
User offline. Last seen 12 years 29 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Unfortunately not. On a similar note, if you reduce the remaining duration of an activity that hasnt started, P3e automatically reduces the Original Duration. This isnt always the desired effect.
Kevin Button
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Steven

Something to try - in the resource assignment detail of the activity, insert a ’Cost Units Linked’ field and untick the box.

Regards