Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Converting P3 file to P6

4 replies [Last post]
Erickson Gapusan
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 23 Jul 2010
Posts: 5
Guys,

Anyone who succeed converting P3 file to P6 with the same Project Completion Date? If anyone does, maybe i’m not doin’ the right way or have just missed adjustment of some part when i’m in access to converted file... Can anyone help me through this sir/maam... Appreciate great guide for this one...


Erick

Replies

Erickson Gapusan
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 23 Jul 2010
Posts: 5
Sir, thank you... I think I missed to check on that part...
Rodel Marasigan
User offline. Last seen 4 days 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Erickson,
Check your Hour per Time Period settings (i.e. 10/d 50/w etc…), it should match the calendar assigned and also check the Global Default calendar which P6 use for calculating total duration on summary band.
Erickson Gapusan
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 23 Jul 2010
Posts: 5
Not actually the error on how to import the P3 file, but rather the adjustment of Project Completion Date after. Imported file does not arrive the same Completion date as calculated in the P3 file...
Rodel Marasigan
User offline. Last seen 4 days 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Erickson,
What is the problem or what the error you’re getting when importing P3 to P6? Is your P3 having WBS define? If not then when running the import wizard and reach to “Update Project Options” click Advance then click Next. Remove all the tick on Project Options and click Finish. That should import your P3 without error.