How to Set up cut-off date in P3

6 replies [Last post]
Angel Cruz
User offline. Last seen 11 years 6 weeks ago. Offline
Joined: 16 May 2010
Posts: 16
In the tabular reports resource loading. For example P3 calculate output with MONDAY cut-off on weekly base. How to set-up cut-off date to FRIDAY?

Replies

Angel Cruz
User offline. Last seen 11 years 6 weeks ago. Offline
Joined: 16 May 2010
Posts: 16
Tnx to all i got it. This forum is amazing...
Anbin Ponnith
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Angel Cruz,
I find another Option also which is very easy
Data->Calender->Click Global Calender->Standard->Week start on -> Change to Saturday
I tried it Just Now it Work
Regards
Anbin
Anbin Ponnith
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Alexandre,

I tried your solution but could not find any option to change the 1st day of the week to Saturday..

Could you please expain me in detail.


With Thanks & Regards,

Anbin Ponnith
Anbin Ponnith
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Hai Angel Cruz
U try the Following Option
1.First Create a new Project(ABC)in that give Week start on Saturday
2.Open your Current Project Select all Activities
3.Click Tools->Fragnet->Store Fragnet->Type Id->Type Title
4.Open the New Project (ABC)Transfer all the Dictonary Like
a.Activity code
b.Resource
c.WBS
5.Tools ->Fragnet->Restore Fragnet->Select Correct ID u Typed Before
6.Select Rename Duplicate Only -> OK
7.Now u Can see the New Project Similar to the Current Project
8.Now U can Try Tabular Report
I Hope it works
Regards
Anbin