Critical Path in P3 w/o Longest Path

2 replies [Last post]
James Braghini
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 51
Groups: None
Does anyone have a better way of creating a filter for a Critical Path without using the Longest Path? I have a job where the total job has negative float however some activities in the critical path string has positive float.

Thanks,
JJB

Replies

Johny Kesserwany
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
you can fix a number for the total float and the filter will display all activities having a TF less than this number...

Total float LT (x)
Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
You seem to infer that all activities listed as being on the critical path must have the same float in order to be a valid critical path. This was never a part of the definition of “critical path.”

Many issues can cause the longest chain of activities to have different float; activity and resource calendars, interruptible activities, start versus finish float, and constraints come to mind immediately. For more on this, I suggest that you review a paper that I once presented titled, “Longest Path Value” on my website at http://ronwinterconsulting.com/published.htm. Good luck!