Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global update to an old program???

4 replies [Last post]
Steve Brown
User offline. Last seen 17 years 10 weeks ago. Offline
Joined: 16 Jan 2008
Posts: 6
How do I update all dates i.e. ES, EF, LS & LF dates for activities in an old program, that I wish to use for a future project?

I thought I could use Global update but can only seem to
update activities with the same start dates and times at any one time.

Replies

Sam Mohan
User offline. Last seen 5 years 6 days ago. Offline
Joined: 17 Dec 2007
Posts: 17
Groups: None
Hi Steve

I am sorry, there is an error in my previous post.
Instead of Early start it should read as Actual start=" "


regards


sam





Sam Mohan
User offline. Last seen 5 years 6 days ago. Offline
Joined: 17 Dec 2007
Posts: 17
Groups: None
if the old program has been run previously you may have to run filter to see constraint dates and remove them and then run Global change to effect the following :
change percent complete(pct)to 0(zero), Remaining duration(RD) equal to Original Duration(OD) RD=OD and Early start ES as " " .
Now schedule with new project start date.

hope this would of help.


regards

sam
Johny Kesserwany
User offline. Last seen 8 years 22 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
Hi,
I did not understand exactly your question...What do you mean by updating an old Program? to be used for a future project? when you do update you’ll get Actual Start, Actual Finish and percent complete...No more ES,EF,LS & LF...Global update? Do you mean ’Update Progress’?
If you want to use the ’old’ program as plan for a future project you can change the Start project date in the project Overview menu and schedule ’F9’ the program, than you’ll get your ES, EF, LS & LF with new planned dates starting from the new project start date...


Concerning the update P3 offers several ways of updating your schedule. You can update progress for all activities and resources as a whole; update activities and resources individually; or use a combination of the two methods.

If your project is progressing exactly as planned or if you only need to estimate progress, simply specify the data date or "as-of" date, then have P3 determine which activities have progressed and how much and calculate the remaining durations of activities that have started. P3 also notes which activities have completed and sets their remaining durations to zero.
If your project is not progressing as planned—many activities are out-of-sequence, activities are taking more or less time to complete than originally planned, or actual resource use is exceeding planned use—update activities and
resources individually. This will help you forecast the effects of this unforeseen progress or lack of progress, so that you can take appropriate corrective action wherever necessary.

Most projects progress somewhere between these two situations: some activities are progressing as planned and
some are not. If this is the case, you’ll want to combine the two updating methods. Let P3 calculate your project as if it is progressing exactly as planned, and then individually update those activities and resources that have deviated from the plan.

Regards
JK
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Steve
ES,EF,LS, and LF are calculated based on a project’s network logic. If there are no acuals, you’ll simply modify the project’s start date and start Tools --> Schedule --> with report. Constraints may harm the calculation. Read the report!
If there are actuals you’ll have to remove them first, by Global Change.
Regards
Dieter