Adjust Working Hours

2 replies [Last post]
Karim Mounir
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi,

When I exported the P3 sch to P5, I got 1 day difference in the early finish of the latest activity in P5.
I consulted the Primavera rep. and he notified me that this is a bug in P5 which they solved in P6.

Is this true?, can I adjust the working hours in P3 to be the same as in P5 (ie. 10 working hours/day) and if so will this solve this issue?

Regards,
Karim

Replies

Karim Mounir
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Thanks JK
Johny Kesserwany
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
Hi Karim,

P3 is based on working days and not on hours. P5 & P6 are hours based and any schedule converted from P3 will have the same problem. P6 too has the same bug.

Regards
JK