Hi,
When I exported the P3 sch to P5, I got 1 day difference in the early finish of the latest activity in P5.
I consulted the Primavera rep. and he notified me that this is a bug in P5 which they solved in P6.
Is this true?, can I adjust the working hours in P3 to be the same as in P5 (ie. 10 working hours/day) and if so will this solve this issue?
Regards,
Karim