Duplication of Milestones

1 reply [Last post]
Cristian Fracelli
User offline. Last seen 17 years 24 weeks ago. Offline
Joined: 9 Jan 2008
Posts: 3
Hello,
my little problem...
I have a milestone that I have to copy in another wbs, with a link FF or SS will always have the same foreseen date, but... when one of these milestone will become actual, the other not...
How can I do so that when one becomes actual the other milestone becomes actual in automatic?


Cheers
Cris

Replies

Johny Kesserwany
User offline. Last seen 8 years 22 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
P3 considers each milestone as an activity, and it’s normal when you actualize one the others remain unchanged! you can do a filter and then update all the milestones responding to this filter...

Regards