Budget quantity for milestones

2 replies [Last post]
Eckart Schenck
User offline. Last seen 4 years 10 weeks ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None
Hi all,

I’m trying to put a quantity onto a milestone (purchase order).
This works fine for actual MS, but not for planned.

Do you know reason for that, is there a way around that?

Thanks for your help!

Heinz

Replies

Gordon Blair
User offline. Last seen 6 years 12 weeks ago. Offline
Joined: 29 Jul 2005
Posts: 166
Groups: None
Umm have you tried just adding it into the cost window?

Resource ’What ever you want to call it’

Budgeted Cost ’how much it is’

As long as you’ve got the relevant resource in the dictionary, doesn’t appear to cause a problem.

This is how I do all my Milestone payments.

Let me know how you get on?

Cheers

Gordon
Gary Whitehead
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 1 Sep 2005
Posts: 69
Groups: None
I’m guessing P3 won’t allow you to add planned resources for a zero-duration task, as it would have problems calculating the forecast when it’s spread across zero time.

As for a way round it, a quick and dirty fix would be to change the Milestone to a normal task with a duration of 1, and correct the schedule with appropriate changes to lags.

Cheers,
G