duration calculation in p3& p5

2 replies [Last post]
Mangesh Khuspe
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
i had to export some progs in p3 for but when i looked at the durations in p3 it had changed
Let me explain in p5
say activity A start date & finish dates are
02/05/07 , 05/08/07.
but same activity A in p3 has start & finish dates
are 02/05/07, 02/08/07.
Calender is same in both,
the relationship remains the same.

then why does it calculate like that?

cheers
mangesh

Replies

Mangesh Khuspe
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
John

Thanks for your help it solved my problem.

Thanks PP


Cheers

Mangesh
John Raper
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
Mangesh

This is only a guess but check it out.
I assume your ’planning unit’ in P3 is ’Days’. In P5 the planning unit is always hours, but appears as days. You will need to check the hours/day in ’Admin|Admin Preferences|Time Periods’. This deterimnes the calculation for hours per day etc.
You may need to change the duration, then change it back, for the duration to be re-calculated.

Hope this helps.