Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

PROGRESS BAR

17 replies [Last post]
Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
I am displaying progress on my actual bar based on remaining duration and expects also that P3 calculates the % complete based on the actual and remaining duration.

However, once I have performed F9, some progress bar are going beyond the data date and my %Complete column is not showing any figures.

Please help

Replies

ulysses garcia
User offline. Last seen 14 years 21 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
as a clients i make sure what method of autocost you are using before updating. may you may violates the contract
Zq qz
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Yes b???y........thats the solution....But make sure it will not violate the contract.

More Power
Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
Thanks Ferdi, it did improve the schedule, % Complete are now showing figures.

I am trying to re-update this schedule, correcting the logic for started activities with out of sequence links. It seems to be the contributor to the progress bar behaviour.

Thanks for the help guys!!!
Zq qz
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Try to locate this in your PC.....Maybe it works


\P3WIN\P3PROGS\PFXW.EXE
Scott McAndrew
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 18 Jun 2007
Posts: 6
Groups: None
If you take a look at the Autocost rules. There is a box that links the RD and Pct. If that box is unchecked then P3 expects you to input the pct complete AND update the RD.

If you check that box and calc the schedule. Ensure that the Autocost rules will be applied when you calc and that should fix your Pct complete issue.

I would also sugest changing the Schedule Options back to retailed logic so that you don’t bypass out of sequence logic.
Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
Yes, I am working on a project with a Target.

The out of sequence activities seems to play a part for the progress bar problem, but could anyone confirm if it also affects the % Complete column.

Though, the progress override solves the progress bar problem, the resulting schedule can’t be used since it bypasses all the built-in logic.

I have heard of P3Fix software, have anyone here used it? and Do you think it will solve the problem that I have?
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
first of all I would like to tell you that i’m not a primavera representative! however, considering that this is free! and i believe open! let me try...

out-of-sequence activities: (please note that this is my personal definition) - activities that have progressed disregarding the originally defined relationships. I’m not really sure if it affects the colors of your bars, just try to play with it!

another thing is, when you’re formatting your bars - go to format bars; Display progress and criticality on Target Bar based on: Current Project or Target Project; you have to chose one!

by the way, are you working on a Current Project with a Target?

can you offer me a job?

Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
Duration is the weighting factor i am using.

Tell me more about out of sequence activities. Doest it affect the progress bar. How about the % Complete column?
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
don’t forget also to chose Duration as your weighting factor, go to tools; options; summarization; check duration

also check the activities that are out of sequence.
Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
I am using retained logic.

Not all progress bar are behaving this way (progress bar going beyond data date).

I am putting actual start date on activities that had started and adjusting the remaining duration for activities in progress.
Kieran Thomson
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 28 Jan 2004
Posts: 43
Groups: None
Are you inputing the actual date started or just changing the remaining duration?
Eliza Cote
User offline. Last seen 14 years 33 weeks ago. Offline
Joined: 19 Jan 2006
Posts: 11
Groups: None
Sometimes when my bars are not behaving correctly it is because I have not correctly input the SCHEDULE/LEVEL Calculation Options.

It can make a difference if RETAINED LOGIC is selected rather than PROGRESS OVERRIDE. I normally operate with PROGRESS OVERRIDE checked off.

Eliza
Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
Thanks for the feedback.

That what I have here, the column %Complete turns 100 once activities are updated as done but does not shows any %complete when activites are still in progress.

I was thinking that if it is a bug that P3 has or any setting I need to adjust to achieve the desired results.

I have tried updating default sample projects and have the same results.
Ashraf Jahangeer
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
There are two things.

1 . The progress bar is going ahead of data date.

2. The progress is not shown in % compl column.

I can undersatnd the 1st case as when we update manually it happens. But for the item 2 it sounds impossible. Check the coulmn I suspect you have Custum data item in it and not the default percent complete.

Regards,

Ashraf
Pablo Jardiniano
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 16
i have tried this solution so many times but does not work.
Ashraf Jahangeer
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi,

Dont assume that calculates the % complete based on the actual and remaining duration.

Set it TOOLS -> OPTIONS -> AUTO COST RULES, Cross the box for LINK REMAINING DURATION AND SCHEDULE PERCENT COMPLETE.

You may have to re-update the progress and scehedule by F9, hopefully your problem will be solved.


Regards,

Ashraf



Zq qz
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
to answer progress is going beyond due to out of sequence logic. This can be solve using progress override.

2nd thing %comp figure not appearing in the column is really a bug.....try to reboot your PC.....