Dates

1 reply [Last post]
Gary Mourfield
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 30 Apr 2007
Posts: 3
What is a "run date" and how is it differentiated from the Data Date.

Replies

Bijaya Bajracharya
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
Run date = the date on which the project was last run (opened). Any change made in activity (for example progressing, changing original or remaining durations)will have effect only in that activity until F9 is pressed (rescheduled).