Adding and Removing Projects from the Master

4 replies [Last post]
Terry White
User offline. Last seen 11 years 49 weeks ago. Offline
Joined: 8 Feb 2004
Posts: 39
Groups: None
I’ve just been spending my lunch hour trying to understand how to remove projects added to a main project when they’re closed out, but still retain the information in the background should I ever need to refer to them again. Is this something that is quick to explain ?

What I need to do is have one Project, i.e. Me and my workload... Into this I setup separate projects as and when which are then linked into the main one. Once a project is finished, it is closed out and doesn’t appear on the Master project anymore.

Can anyone advise me how to go about doing this please ?

Replies

Ashraf Jahangeer
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Terry,

I also encountered the same trivia while working on my project. Although the project is closed still for historical records it has to be retained in the system.

What I do is make a copy the project and then delete the original from the master. As to add the project again to master I again copy the project in the master project group.

Hope this clarifies your querry.

Regards,

Ashraf
Terry White
User offline. Last seen 11 years 49 weeks ago. Offline
Joined: 8 Feb 2004
Posts: 39
Groups: None
This may sound like a silly question, but how do you ’Close’ a project please ?

Thanks