Project / Activity Dates

22 replies [Last post]
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
once again, another question i’m sure you will all find remarkably easy,, i have a project containing numerous activities all with different Early Start/Finish Dates, i have been asked to run some different scenarios in changing the project dates (we are governed by the arrival of an accomodation barge) i have tried changing the date on the Data Date line but this does not change the dates of all of the activities, is there a method of changing all of the activity dates in one hit to give figures for differnet scenarios?
many thanks

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

you don't really specify a new start date for each activity that what the logic and durations are for. Progress the activities accordingly with actual start and or finish dates and change the remaining duration if the activity is in progress and not complete. Then move the data date and re-schedule the project.

Syam Mohan
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 26 Mar 2016
Posts: 5
Groups: None

Hi everyone,

                  In my p6 software dates are not changing for particular activities according to the relation given. The calender assigned is same for all activities. Please help me with your valuable suggestions to fix this.

Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Which probably means that you dont have any Early Constraints set
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
i’m getting
invalid data item/value

Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Needs to be

SNE EQ
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
sorry Steven,
i’m getting an error the reads - Invalid Criteria Code

i have nothing other than SNE in that row now
under that row i have this:
MS EQ ES - 20
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
yep
Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Nothing, all it is doing is removing any existing constraints, as in P3 an activity can only be assigned one type of constraint.
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
what do i need to enter in the Data Item/Value column on the same row as SNE?
i.e
then SNE EQ ___
Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
If you are trying to overrule the logic of your schedule, you will need to use Mandatory Constraints.

On the change tab of Global change

If Act Cn "SYS"

Then SNE = ’ Removes any existing constraints
MS = ES - 20


Then re-schedule

Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
that is correct
- sorry if i’m talking in riddles

Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
To try and phrase your question into english, is it

If
Activity ID Contains "SYS"
Then
Constrain the start to 20 days prior to the current early start ?
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
this will be the very last question on this subject:
when i apply the Global change (i have made several copies of my Plan so i’ve got back-up), do i enter the criteria on the Change of the Selection tab? i assume it is the Change tab, when i have runu this i get the error that the activities already exist??
the criteria i enter are as follows:

IF : ACT | CN | SYS (my activity codes i want to change) | - | 20d.

THEN: ACT | CN | ACT


thanks again
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
thanks Steven thats great
Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
SNE = es + 10d


for instance
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
how do you specify a new start date for activities in a global change? sorry to keep asking these tedious questions
Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
You could use a combination of activity codes and global change, if you have a lot of changes, but a well constructed schedule is by far the best option.
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
,, so would i have to change the constrains on each individual activity or is there a method of group change? obviously alot of the activitis start at later dates in the schedule, i have many activities running in different calendars so if changing the constrains is the best method i woould rather use this,,
thank you very much for your help
Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Thats because the activities placement in time is dictated by the logic in the schedule. If you need to impose a different start/finish, then use constraints or calendars
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
, sorry, one more, that works when the scheduled data date is taken forward, what about when the scheduled data date is taken back? the line moves but the activity dates stay where they are?
Jonathan Ward
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
thats got it,, thanks again
Steven Oliver
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Isnt that what scheduling is supposed to do ?