Resource Loading

9 replies [Last post]
rehan abbasi
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 5 Dec 2006
Posts: 6
This entering resource for each & every activity is becoming a tedious and time consuming process process for me, does any one have any easier and faster solution for it.

Replies

Hassan Emam
User offline. Last seen 18 years 7 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
Actually i’m familiar with VB. I’ll try my best with this and any questions i’ll come back to you

Thanks all
Rodel Marasigan
User offline. Last seen 23 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Ifeanyi/ Hassan,

Just for additional info. Both RA/ Excel utils and export/ import under P3 utilities have same result on P3. You can choose which one can suit best for you. Be sure to understand the logic and procedure on how to do it and I recommend doing a lot of practice before using it on a live project. Also be aware to delete the existing link or logic before importing a new logic to the same activities otherwise you will end up of multiple link on same activities. If your familiar with visual basic, that will help a lot. Enjoy planning.

Cheers,

Rodel
Hassan Emam
User offline. Last seen 18 years 7 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
Thanks Mate let me try it
Ife Olyke
User offline. Last seen 11 years 1 week ago. Offline
Joined: 6 Feb 2007
Posts: 147
Thanks Mimoune.
mimoune djouallah
User offline. Last seen 5 years 48 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
Hello Ifeanyi

RA it is a kind of API to access functionalities of P3, and it can be used with many programming language,
If you go to P3M\Ra\Samples\EXCEL( in your installation CD ROM) you will find some sample excel files using Macro (visual basic for application ;)

You can use them to update many things in your schedule like resources. sometimes it is better to introduce data in a spreadsheat software then in the old fashion P3

HTH

mimoune
Ife Olyke
User offline. Last seen 11 years 1 week ago. Offline
Joined: 6 Feb 2007
Posts: 147
Hi Rodel,

I am also interested in knowing what you mean by RA/Excel in P3.1. However, my understanding of your earlier comment is simply put this way:

Take export of the plan specifying the content, format and selection to excel,

Update the resources in excel,

Import to the plan.

I hope we are on the same page.

Ife
Hassan Emam
User offline. Last seen 18 years 7 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
Can you explain more wht do you mean by RA/Excel
rehan abbasi
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 5 Dec 2006
Posts: 6
Thnx Rodel. Certainly made my job a lot easier.
Rodel Marasigan
User offline. Last seen 23 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Try RA/Excel utils in P3.1 or Export/Import in P3e

Regards,

Rodel