Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration Summary

2 replies [Last post]
Weni Samson
User offline. Last seen 18 years 24 weeks ago. Offline
Joined: 18 Nov 2006
Posts: 18
Groups: None
Hi there! Can anyone help me on how to put a duration summary per activity codes or per WBS or per level? I am trying to put a summary duration on each level so that it would be easier for me to identify the complete duration of each level. Thank you with much appreciation.

Replies

Alex Wong
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Jose

You may be left out the third option "Hammack Activity" and this may be one of the best option

Why
WBS you cannot link a relationship to the summary, and it a rigid structure so once setup its very hard to change the level

Code structure in Layout
Yes it is very flexible, but again you cannot link the summary bar with the actual activity.

So my suggestion is depend you need Code structure and Hammack is you best options

HTH

Alex
Jose Frade
User offline. Last seen 4 years 15 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hello,

Several options depending on how you organised the sturcture of your project.

Option 1 WBS

Imagine you created a wbs code like this
10. Engineering
10.10 Basic
10.10.10 Process flow Diags.
10.10.20 Layout
10.20.30 etc

then you have to attribute to each activity one of this codes.

After, you can create one activity type (example) WBS with code 10.10 - this activity will summarize all activities under code 10.10 .

Option 2
Summarize by layout
in the stucture of your database create the necessary codes for the summary phase you want (Eng. / Procurement / manufacturing / transport / construction / erection / commissioning / etc).

Then sort the activities by phase code and ask to have the summary bar (top or bottom).

I hope to have been of any help.

BR
JMFrade