Hi,
I wish to know how you deal when project is underway and you have to record the progress when new items or new job have been added to your original contract. For example, lets take the following example:
Activity   Estim. MH    Weight   Progress  Earned
--------   ---------    ------   --------  ------
Act. 1      150           15%      100%     150
Act. 2      250           25%       60%     150
Act. 3      200           20%       15%      30
Act. 4      180           18%        0%       0
Act. 5      220           22%        0%       0
          ---------     ------   --------  ------ 
   Total   1000          100%       33%     330
Now, management or customer instructs you to add one more activity. Note that the Estimated Mhrs will increase, the distribution weights will change per each activity, and therefore the overall progress (based on resource) will also change (lower).
Activity   Estim. MH    Weight   Progress  Earned
--------   ---------    ------   --------  ------
Act. 1      150           14%      100%     150
Act. 2      250           23%       60%     150
Act. 3      200           18%       15%      30
Act. 4      180           16%        0%       0
Act. 5      220           20%        0%       0
Act. 6      100            9%        0%       0 
          ---------     ------   --------  ------ 
   Total   1100          100%       30%     330
Is this right? You had 33% of overall progress before the new activity came up; now you have 30% with the new calculations. Please, let me know if Im doing something wrong or if this ok or what approach you use. I will welcome your comments and opinions on this issue.
Thank you very much.
       
          