Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3 schedule from mandays to manhours

6 replies [Last post]
Jeffrey Newman
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 27 Jul 2005
Posts: 16
I am currently on a project that has been resoursed in mandays, but we are finding it inaccurate when cosidering Earned Value. I have been asked whether we can change the resourse units from mandays to manhours, is there a quick solution to this using P3? Help!

Replies

Alex Rozenkevich
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 19 Aug 2004
Posts: 21
Groups: None
Hi,

The project I’m on we dont have money uploaded and to be able to show both mandays and manhours I assign a cost of 10 for each manday. Earned Value can be calculated for both, you just specify whether it’s resource or cost based.

Hope this helps.

Alex
Sukumaran Subaram...
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Jeffrey,

If you want to change from mandays to manhours:
a) check what is the allocated working hours per day.
b) make a copy of the current file and change the planning unit to hour.
c) then do all the necessary changes using global change.

If you just change the duration to manhours than I don’t think there is any significant effect because you are merely converting the duration from 1 day to 24 hours, which is generally the same. That means your EV is still the same as before.

Regards.
Raja Izat Raja Ib...
User offline. Last seen 12 years 51 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Steve,
Nothing will effect EV, We just mutiply Mandays to Manhours in GlobalChange and generate in report writer but if we change the origin Data from Mandays to Manhours of cause it will totaly change the EV. It will create more works to be done.
Steven Oliver
User offline. Last seen 11 years 26 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
What effect do you think this will have on the way Earned Value is calculated ?
Peter Bailey
User offline. Last seen 18 years 19 weeks ago. Offline
Joined: 18 Aug 2005
Posts: 10
Hi Jeff,

You can try to copy the project (Tools, Project Utilities, Copy) and then change the planning units there. You can then make the changes using Global Change
Raja Izat Raja Ib...
User offline. Last seen 12 years 51 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Jeff,
I suggest u use global change.