Total Project Manhours/mandays

6 replies [Last post]
JEEV RAJ
User offline. Last seen 20 years 10 weeks ago. Offline
Joined: 6 Oct 2003
Posts: 4
Groups: None
In Primavera Project Planner which is the best way to know total manhours/mandays on the project

Replies

Zq qz
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
You can also do it using report writer.
Jorge Taguinod
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
You may also want to use cost categories (e.g. L-Labor, M-Material, E-Equipment, etc.) If you do this, then you could simply organize by cost categories and summarize to get your totals.

Hope this helps.

Jorge
Gilbert Rayco
User offline. Last seen 7 weeks 6 days ago. Offline
Joined: 24 Feb 2003
Posts: 20
Dear Jeev,

I’m confident that it can be done as long as u identify
individual equipment in ur resource library.

Good day,

G. Rayco
JEEV RAJ
User offline. Last seen 20 years 10 weeks ago. Offline
Joined: 6 Oct 2003
Posts: 4
Groups: None
Gilbert,

Thanks for your response. I will work on this approach and also see if same can be applied for individual equipments too.

Jeev
MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
No report until you have assigned human resources to activities.
Gilbert Rayco
User offline. Last seen 7 weeks 6 days ago. Offline
Joined: 24 Feb 2003
Posts: 20
Dear Jeev,

IMHO For quick report:
- tools, tabular reports, matrix, resource/cost
or
- tools, tabular reports, resource, tabular

Hope this will help

G. Rayco