Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Update discrepancy

9 replies [Last post]
Ismail Vandeliwala
User offline. Last seen 13 years 2 days ago. Offline
Joined: 11 May 2004
Posts: 23
Groups: None
Currently after update i have found a peculiar situation in my update. There is an activity with a single predecessor and successor, the total float of this activity is very high and in no way co-relates to the backwardpass calculations of the schedule. Both the predessor and the successor of the activity have a FS link.

Has anyone experienced this before and can explain to me why it is happenning and what’s the solution.

Replies

Ismail Vandeliwala
User offline. Last seen 13 years 2 days ago. Offline
Joined: 11 May 2004
Posts: 23
Groups: None
Thanks David you were right.
Ismail Vandeliwala
User offline. Last seen 13 years 2 days ago. Offline
Joined: 11 May 2004
Posts: 23
Groups: None
hi, thanks for all the suggestion.

Finally managed to figure out the problem. the current problem that i am facing with the float is due to the Scheduling option being set to Progress Overide. Once it has been reset to retained logic then the floats are ok.
Philip Jonker
User offline. Last seen 16 years 47 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
[Deleted by Moderator.]
Ismail Vandeliwala
User offline. Last seen 13 years 2 days ago. Offline
Joined: 11 May 2004
Posts: 23
Groups: None
thanks for the response..........but the activity is not an open ended activity. it has a successor with a finish to start link and the successor has a negative float.

Sukumaran Subaram...
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Check the last activity in the sequence. If the activity is left as an open end, link it to the nearest next relevant activity and re-calculate the schedule.

Regards.
David Andreotti
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 6 Jul 2005
Posts: 47
Groups: None
Any chance you have Progress override turned on? Or maybe you need to run the pfxw utility.

Ismail Vandeliwala
User offline. Last seen 13 years 2 days ago. Offline
Joined: 11 May 2004
Posts: 23
Groups: None
i checked the calender first, that’s the same as the project calender and the same for the activity and it’s predecessors & successors
Suraj Bhatt
User offline. Last seen 11 years 8 weeks ago. Offline
Joined: 24 May 2004
Posts: 58
Groups: None
I think calendar might be a problem.Just check the activity calendar..is it same as the project calendar?
Raj Maurya
User offline. Last seen 4 years 17 weeks ago. Offline
Joined: 17 Jul 2004
Posts: 132
Ismail,
If everything is ok as per suggestions of other planners and you still have same problem try to add a new activity with same duration and dependencies and see if this give correct float?