wbs on activity bar

3 replies [Last post]
Rajeev Kumar
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 27 Apr 2003
Posts: 43
Groups: None
Can somebody tell me how I can show the WBS description on the activity bar?

Replies

MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
By export/import or by RA, fill a log by WBS description, then display the log against activity bar
Steven Oliver
User offline. Last seen 11 years 23 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
limited success can be achieved using a Custom Data Item, and Global Change to set the value of your CDI = WBS Title. However the limit for a CDI is 20 characters, so you would have to limit the WBS Title to this.

As an alternative you could export the activity ID to Excel and assign the WBS Title as an activity log, then upload these values back into P3 (a bit messy!).

Paul Harris
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
I do not think this may be done.

The bands may be extended over the bar chart area and the WBS description shown here, but this is not quite the same.

You could produce a WBS activity for each WBS code, make the description the same as the WBS code and filter on just the WBS activities. Still a bit of messing around.

Regards

Paul E Harris
www.eh.com.au