rebaseline

6 replies [Last post]
Forum Guest
User offline. Last seen 48 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None

how does primavera rebaseline when tracking project

i want to understand how p3 resolve the problem of new BQWS with the BQWP

you know that when you want to re-baseline a project
you must to put BQWS=BQWP

i want to know how p3 do that

is it with " GLOBAL CHANGE" or something else

i’m here for more explications

thank for your help

Replies

Zq qz
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Another method is using your current schedule as your target
Bensouyah Mohamed
User offline. Last seen 17 years 15 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 7
next time i’ll give u a real example of project
MK TSE
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Make use fields, like custom data fields, to store some calculated values in step by step calculation.
The whole process is control by global change.
Zq qz
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Another method is Update Target Option
Forum Guest
User offline. Last seen 48 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
please more explications
MK TSE
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
by global change to update the required field(s).