how does primavera rebaseline when tracking project
i want to understand how p3 resolve the problem of new BQWS with the BQWP
you know that when you want to re-baseline a project
you must to put BQWS=BQWP
i want to know how p3 do that
is it with " GLOBAL CHANGE" or something else
im here for more explications
thank for your help