Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Logic of completed activities

2 replies [Last post]
Joe Mansour
User offline. Last seen 3 years 4 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
After completing the schedule and its successive updates until the project completion, is there a way to get a report about the validity of the original logic of the schedule? In other words, suppose we have to redo the schedule for the same project, how can we get a report from the completed project about the corrections we should make for the new schedule?
Appreciate your replies.

Joe

Replies

Gilbert Rayco
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 24 Feb 2003
Posts: 20
Dear Joe,

P3 can provide u a successor report by:
- Tool, project utilities,export
- choose EX-12, modify per ur requirement
above is effective only if u have maintained a good
records/corrections which are reflected in the as-built planned. otherwise it will not be of help, it can be done but it will be tedious process.

Hope this can assist u


G. Rayco
MK TSE
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
In P3, the linkages of a activity are maintained and not deleted even it is completed.
Prepare a prec and succ text report or Export the succ report will have the data