P6 WBS is Hierarchy is mismatching in activity Window

No replies
Rajkumar S
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 4 Nov 2011
Posts: 9
Groups: None

Hi, I required troubleshooting in my P6, The WBS Hierarchy sequence is not followed in my activity window in my P6. This started when I imported an external .exr file into my P6. My whole P6 has started to follow the WBS disturbance. The screenshots are enclosed. Anyone Welcome to provide a solution. Thank you

8471
wbs_1.jpg
8472
wbs_2.jpg

david kelly
User offline. Last seen 5 days 4 hours ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

You should always zero fill in P6.

For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1

Just overtyping the WBS code with the new zero filled values should sort it