SAP Task List Operations

2 replies [Last post]
Aaron Morris
User offline. Last seen 7 weeks 4 days ago. Offline
Joined: 10 Oct 2019
Posts: 5
Groups: None

Hi there,

I've been tasked with reviewing what our requirements are for the creation of new operations within a task list. The below requirements are what we have in our documentation but this has resulted in some tasks having over 100 operations to feed into a Gantt chart. Would really appreciate some improvement suggestions.

An independent operation is any operation which has any of the following differences:

  • Type of work to be performed is different from previous work operation.
  • The resource work centre required to complete the work is different, if not part of the crew already completing the works.
  • Number of hours, or personnel, to complete the work is different.
  • Specific materials or services are required against a specific operation.
  • Specific work instructions are required to be assigned to a specific operation

Regards,

Aaron

Replies

Aaron Morris
User offline. Last seen 7 weeks 4 days ago. Offline
Joined: 10 Oct 2019
Posts: 5
Groups: None

Thanks for the feedback Vladimir. I think that certainly helps to clarify the requirement a bit better.

An independent operation is any operation which has any of the following differences:

  • Type of work to be performed is different from previous work operation
  • Work amount (volume) unit is different
  • Resource crew is different
  • Resource productivity is different
  • Material requirements are different
  • Unit cost is different
  • Work calendar is different
  • Dependencies are different