Hi there,
I've been tasked with reviewing what our requirements are for the creation of new operations within a task list. The below requirements are what we have in our documentation but this has resulted in some tasks having over 100 operations to feed into a Gantt chart. Would really appreciate some improvement suggestions.
An independent operation is any operation which has any of the following differences:
- Type of work to be performed is different from previous work operation.
- The resource work centre required to complete the work is different, if not part of the crew already completing the works.
- Number of hours, or personnel, to complete the work is different.
- Specific materials or services are required against a specific operation.
- Specific work instructions are required to be assigned to a specific operation
Regards,
Aaron