Primavera Duration Types

4 replies [Last post]
Debosky Wale
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 16
Groups: None
Hi all, could someone please explain with scenario/examples different duration types in P6. I am struggling to understand when to use what I.e fixed duration & units, fixed united etc. Appreciate your anticipated help, thanks

Replies

Kathy Castle
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 17 Apr 2018
Posts: 22
Groups: None

Primavera P6 duration types have affects on activity duration, resource and cost distribution when progressing the schedule. Activity durations control the critical path and the completion date of a project. You can read this article about the Primavera Duration Types

Khuong Do
User offline. Last seen 1 year 49 weeks ago. Offline
Joined: 21 Feb 2010
Posts: 118
Groups: None

Hi.

I wrote an article to explain How to use Activity Duration Type in Primavera P6.

Kindly read it here https://doduykhuong.com/2018/03/25/how-to-use-activity-duration-type-in-primavera-p6/

Cheer

Debosky Wale
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 16
Groups: None
Thanks Tom, well understood.
Tom Boyle
User offline. Last seen 1 week 1 day ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

From P6 online help:

  1. Select the duration type:

    Choose Fixed Units/Time if you want the resource units per time to remain constant when the activity duration or units change. This type is used when an activity has fixed resources with fixed productivity output per time period. You most often choose this duration type when you are using resource dependent activities.

    Choose Fixed Duration & Units/Time if you want the activity duration to remain constant and the remaining units to change. This type is used when the activity is to be completed within a fixed time period regardless of the resources assigned. You most often choose this duration type when you are using task dependent activities.

    Choose Fixed Units if you want the activity units to remain constant when the duration or resource units per time change. This type is used when the total amount of work is fixed, and increasing the resources can decrease the activity duration. You most often choose this duration type when you are using resource dependent activities.

    Choose Fixed Duration & Units if you want the activity duration to remain constant and the units/time to change. This type is used when the activity is to be completed within a fixed time period and the total amount of work is fixed. You most often choose this duration type when you are using task dependent activities.

Note

  • The Duration Type field is disabled if the Activity Type is Start Milestone or Finish Milestone.