How to Build a level 5 schedule using PowerPivot

No replies
mimoune djouallah
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

here is a free template using Excel 2013, no VBA is required, you need Powerquery Installed

 

the template use a schedule forecast data ( P6, P3, Ms Project etc) and the MTO data to generate any Gantt chart you may think of

 

https://datamonkeysite.wordpress.com/2016/11/11/how-to-build-a-level-5-s...

 

want, schedule by tag, and area fine, construction by subsystem etc

 

comments are welcome