P6 Calendar - Shift working

1 reply [Last post]
ashish karanjavkar
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 11 Feb 2014
Posts: 2

Hello Everyone,

I have 2 criterias for an activity

1. It can be done only in Day time (0600 to 1800)

2. Activity cannot be left undone even if its 90% finished.

e.g. Activity duration is 4 Hrs. and its starting on 1500 - then it should automatically moved onto next day.

While doing baseline i managed to make it happen wih help of Constraints & change in logic.

However, my worry is while in operation if this situation arises then P6 will just schedule it with current logic. that means activity will be split between 2 Days (1500 to 1800 3Hrs + 0600 to 0700 1hrs next day).

 

Is there any way to get this things right throughout?

Replies

Ashish,

what you are looking for is an activity property in Spider Project (if its execution shall be continuous or not necessarily) but I did not meet this functionality in other packages including P6.