CPM and PDM methods

3 replies [Last post]
Labros Kolias
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 7 Oct 2015
Posts: 2
Groups: None

Hello to everyone, i'm running a dissertation about project management and i would like to ask about those two methos.

I want to know if we run the same project with CPM and then with MPM do i expect always the same resuls? Are there any articles about that?

And who do you think is the best option between those two?

 

Thank you!

Replies

Patrick Weaver
User offline. Last seen 4 days 22 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

Hi Labros,

ADM and PDM (in the title) are both variants of CPM developed in the USA.

ADM = Arrow diagramming Method (the original CPM technique)

PDM = Precedence Diagramming method

CPM = Critical Path method (ie, a single deterministic duration estimate).

MPM = Meta Potential Method, was developed in Europe around the same time as PDM but independently.

For more on the developments see: http://www.mosaicprojects.com.au/PDF_Papers/P042_History%20of%20Scheduing.pdf 

MPM uses a single duration estimate but has more link options than PDM. PDM has the 4 link types FS, SS, FF and SF only and these can be implemented differently in various software tools to create different answers.  MPM adds a number of other variants. Generally, the two processes will get similar results, the real difference though will be in the way different software tools deal with conflicts created by different link types. 

For more on links see: http://www.mosaicprojects.com.au/PDF/Links_Lags_Ladders.pdf 

For more on calulations see: http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf 

 

Patrick Weaver
User offline. Last seen 4 days 22 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

Hi Labros,

ADM and PDM (in the title) are both variants of CPM developed in the USA.

ADM = Arrow Diagramming Method (the original CPM technique)

PDM = Precedence Diagramming Method

CPM = Critical Path Method (ie, a single deterministic duration estimate).

MPM = Meta Potential Method, was developed in Europe around the same time as PDM but independently.

For more on the developments see: http://www.mosaicprojects.com.au/PDF_Papers/P042_History%20of%20Scheduing.pdf

MPM uses a single duration estimate but has more link options than PDM. PDM has the 4 link types FS, SS, FF and SF only and these can be implemented differently in various software tools to create different answers.  MPM adds a number of other variants. Generally, the two processes will get similar results, the real difference though will be in the way different software tools deal with conflicts created by different link types. 

For more on links see: http://www.mosaicprojects.com.au/PDF/Links_Lags_Ladders.pdf

For more on calculations see: http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf

Patrick Weaver
User offline. Last seen 4 days 22 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

Hi Labros,

ADM and PDM (in the title) are both variants of CPM developed in the USA.

ADM = Arrow diagramming Method (the original CPM technique)

PDM = Precedence Diagramming method

CPM = Critical Path method (ie, a single deterministic duration estimate).

MPM = Meta Potential Method, was developed in Europe around the same time as PDM but independently.

For more on the developments see: http://www.mosaicprojects.com.au/PDF_Papers/P042_History%20of%20Scheduing.pdf 

MPM uses a single duration estimate but has more link options than PDM. PDM has the 4 link types FS, SS, FF and SF only and these can be implemented differently in various software tools to create different answers.  MPM adds a number of other variants. Generally, the two processes will get similar results, the real difference though will be in the way different software tools deal with conflicts created by different link types. 

For more on links see: http://www.mosaicprojects.com.au/PDF/Links_Lags_Ladders.pdf 

For more on calulations see: http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf