Dear All,
I need your expert advice on the following so plaese refine the below answers
1) What are basic principles and logic behind to prepare Target Programme when the Contract Programme is already in place?
Ans: Target Programme is the detailed programme which we prepare by adding new activities, changing the sequence and logic of contractual activities as per Site conditions to meet the Contractual finish date or complete the project at earliest
2) Why your Target programme looks entirely different from Contract Programme in respect of arrangements of activities?
Ans: We need to complete the project in time. To achieve this aim and to make the programme more realistic and workable we shuffle the activities, add new activities etc. So this does not make any difference that our Target Programme does not have the same sequence as of Contract Programme.
Ps. Mike testro : if you could reply, it would be great help
The earliest reponse would be appreciated
Regards
Steve
Replies