Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Tunneling -Drill & Blast Excavation rates

3 replies [Last post]
Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Not really my area, so I thought I'd ask the brains trust:

I have a tunnel section of 6m x 8m to be excavated in Granitic material which is likely to be fairly massive. Approx tunnel Length 15km with a mid point adit so each drive is 3-4km. Expectation is that the majority of the drive is Class I requiring minimum support.

My current finger in the air is 6 - 10m/day, but does anyone have any cycle times / excavation rates that I can compare against? There's nothing in the rates area of PP.

I understand some tunneling projects utilise an in-tunnel crusher and conveyors in an effort to boost production. Has anyone direct experience of this?

 

Much obliged,

 

G

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Gary

I have no experience of this operation but I would consider the following after the adit has been constructed and the advance chambers have been cleared by rock drills and hand removal.

Both tunnels can be drilled and loaded simultaneously.

A rock drill can penetrate 1m and will probably take 30 mins to drill.

A 6x8 tunnel with drilling @ 2m centres will require 12 drillholes - using two drills = 3hrs drilling.

say an hour to load the charges and safety check plus 30 minutes evacuation = 4.5 hrs per blast.

say 30 mins for dust extraction and return to shaft.

Hand load debris onto conveyor belt 30 mins.

Equals 5.5 hrs per m converts to .18 m per hour x two tunnels = .36 m per hour.

A 24 hour shift will convert to 8.73 m per day - 4.36 m per tunnel.

Trimming and extraction will be concurrent with drilling and charging.

Miners can ride the conveyor before the charging operation and return the same way.

I hope that helps.

Best regards

Mike Testro

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Thanks for the link Johannes

 

An interesting read, but this was constructed using a TBM rather than via drill and blast, so it's not relevant to my tunnel.

 

Thanks anyway!

 

G

Johannes Vandenberg
User offline. Last seen 8 weeks 6 days ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Gary

This may be interesting link. The Westerscheldetunnel was some years ago built in the Netherlands. The content is in Dutch but with Google translator in should be possible to "read "the  document. Very interesting is the production rate of 12 meters per day.

Regards

Johannes

 

http://www.westerscheldetunnel.nl/nl/over-de-tunnel/tunnelweetjes/tunnel-facts-en-figures.htm