Structural Steel work and Pedestrian Bridge sequence of work needed

1 reply [Last post]
Project Planner
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 16 Apr 2014
Posts: 4
Groups: None

Hi, can someone help me with the sequence of work for construction of PEDESTRIAN BRIDGE, also need one for STRUCTURAL STEEL FRAMING (construction of warehouse or workshop,hope this help).

my email is :  Use private message system

Replies

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Project - welcome to Planning Planet.

What type of structure is your bridge? Steel - Concrete - Insitu - prestressed?

The wharehouse is simple:

Piling > Pads > Sub Base > Steel Frame > Roofing > Drains > Concrete Floor > Cladding > Finish.

Best regards

Mike Testro