WBS & activities percentage refelection issue

1 reply [Last post]
Rana Muhammad Sh...
User offline. Last seen 3 years 39 weeks ago. Offline
Joined: 28 Feb 2014
Posts: 3
Groups: None

i prepared plan. later on i added few WBS along with activities. when i updated plan i am facing following problem.

The activities are showing performance and schedule percentages where as newly added WBS are not showing percentages.

Kindly guide me to rectify this error.

Replies

Jerome Odeh
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 19 Jan 2004
Posts: 102

Your schedule needs to be cost loaded for progress to roll-up to WBS level.

Assign cost to the new activities and their WBS will display performance & schedule % completes.