Successors calapse when manually starting or completing a predecessor

5 replies [Last post]
Charlie Daniels
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 29 Nov 2013
Posts: 12
Groups: None

Hi,

 

When I manually tick the start option of a task and then hit shedule, the successors will fall back to the data line.

 

The same thing happens when I Manually complete a task the successors will fall back to the dataline.

 

Is there anyone with a solution to this problem?

 

Thanks

 

P.S. Manually complete or start meaning not with the datadate update.

Replies

Sendhil Kumar
User offline. Last seen 8 years 46 weeks ago. Offline
Joined: 7 Aug 2010
Posts: 6
Groups: None

Hit F9 --> Options --> "General" tab --> check retain logic option.

Charlie Daniels
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 29 Nov 2013
Posts: 12
Groups: None

HI Anas

"You are probably suing progress override option in the advinced schedule options menu. Change this option to retained logic and successors will not fall back on the data date."

 

Where do I find this option, I am using P6.7?

 

Thanks

Anas Nasr
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 24 Jan 2014
Posts: 2
Groups: None

You are probably suing progress override option in the advinced schedule options menu. Change this option to retained logic and successors will not fall back on the data date.

Rafael Davila
User offline. Last seen 1 day 3 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Are the actual start/end dates you are manually entering earlier or later than the data date?

 

When you say "fall back" to the data line, do you mean the successors become later than they were showing before you scheduled, or earlier?